MIDHUN DAS |
Date: 01/04/2025 |
Work in progress | 15% Completed
|0% Completed
d/s side protection dewatering work in progress
MIDHUN DAS |
Date: 24/03/2025 |
Work in progress | 15% Completed
|0% Completed
side protection piling work in progress
MIDHUN DAS |
Date: 17/03/2025 |
Work in progress | 15% Completed
|0% Completed
8 pile of regulator portion and 125 piles for left side retaining wall in U/s & D/S portion completed.
Nithin J B |
Date: 26/07/2024 |
Work in progress | 2% Completed
|0% Completed
Ring bund work for left abutment portion executed. Ring bund for a length of 60m parallel to river flow executed. But earth filling pending. Pile concrete for 2 piles out of 4 for left abutment portion executed