Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Aug 2022 PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -3955m. PVC pipe - Total 43585/ laid -25490 m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 10300 m. 9 LL OHSR Vadachira - RCC work up to cover slab completed, Plastering work in progress. 7LL OHSR Nirappath - cover slab work in progress. PWD NH Road Cutting permission need to obtain for NH 766 (14.9), PWD Road cutting permission need to obtain for 1 roads. Total bill summitted 145477421.00(contractors bill - 114186142.00) -(PWD - 31291279.00). PACKAGE 2 - Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 2545 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 39350m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 12712 m. Municipality road reformation work in progress.Valve chamber and MS work in progress. PWD road cutting permission need to obtain for 1 road. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766). Total bill Submitted- 126392110.00 (Road reformation - 34,118,511.00 , Contractors bill - 92273599.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2154.5 m. PVC pipe total - 39573 m / Supplied 39534m / laid 34050 m. PVC & MDPE for service connection Total - 23396 / Laid 9900 m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Valve chamber 4 Nos completed. PWD NH road cutting permission need to obtain for 3.5 Km. Total bill submitted -39895590.00/- ( Road reformation - 4196309.00,contractors bill - 35699281.00). DBA
22 Aug 2022 PACKAGE 1 - Pipe supply completed. DI pipe - Total 22142 / laid -5100m. PVC pipe - Total 43680/ laid -38200m. 20 mm MDPE for service connection - 87570 m / Supplied 20000 m / laid - 15000 m. 9 LL OHSR Vadachira - RCC work and Plastering work completed, Painting work in progress. 7LL OHSR Nirappath - RCC work and Plastering work completed, Painting work in progress. Valve chamber work in progress. PWD NH Road Cutting permission need to obtain for NH 766 (14.9), PWD Road cutting permission need to obtain for 1 roads. Total bill submitted 16,56,12,630.00 (contractors bill - 13,43,21,351.00) -(PWD - 3,12,91,279.00). PACKAGE 2 -Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 2545 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 44300m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 14600 m. Kalluvayal distribution system partially charged. Municipality road reformation work in progress. MDPE pipe laying, Valve chamber and MS work in progress. PWD road cutting permission need to obtain for 1 road. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766). Total bill Submitted- 126392110.00 (Road reformation - 34,118,511.00 , Contractors bill - 92273599.00) PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2210 m. PVC pipe total - 39573 m / Supplied 39534m / laid 34150 m. PVC & MDPE for service connection Total - 23396 / Laid 12800m. Kallupady OHSR retaining wall completed. Kaduvakuzhi retaining wall completed. Valve chamber 8 Nos completed. distribution from 7 LL OHSR Kaduvakuzhi partially charged. 700 FHTCs completed. connection work in progress. PWD NH road cutting permission need to obtain for 3.5 Km. Total bill submitted -39895590.00/- ( Road reformation - 4196309.00,contractors bill - 35699281.00). DBA
22 Aug 2022 PACKAGE 1 - Pipe supply in progress. DI pipe - Total 22142 / supplied 14541 m / laid -2987m. PVC pipe - Total 43585 / Supplied 22842 m /laid -20280 m. 40 & 20 mm PVC & 20 mm MDPE for service connection - 87570 m / Supplied 15000 m / laid - 6900 m. 9 LL OHSR Vadachira - base slab and side wall concrete completed, cover slab centering and shuttering completed, reinforcement work in progress . 7LL OHSR Nirappath - base slab RCC completed, Side wall RCC in progress. PWD NH Road Cutting permission need to obtain for NH 766 (14.9), PWD Road cutting permission need to obtain for 1 roads. Total bill summitted 104,621,093.00(contractors bill - 79,961,582.00) -(PWD - 24,659,511.00). PACKAGE 2 -Pipe supply completed. DI pipe Total - 6690 m / Supplied 6682.5 m / laid 1697.5 m. PVC pipe Total - 52815 m / Supplied 52824 m / laid 34090 m. PVC & MDPE for service connection 66780 m / supplied 35000 m / laid 9100 m. Municipality road reformation work in progress.Valve chamber and MS work in progress. PWD road cutting permission need to obtain for 1 road. PWD NH road cutting permission need to obtain for 0/000-5/590 Km (NH766). Total bill Submitted- 103,293,550.00 (Road reformation - 34,118,511.00 , Contractors bill - 69,175,039.00). PACKAGE 3 -Pipe supply completed. DI pipe total - 2948 m / Supplied 2944.5 m / laid - 2154.5 m. PVC pipe total - 39573 m / Supplied 39534m / laid 33000 m. PVC & MDPE for service connection Total - 23396 / supplied 10000 m / Laid 9900 m. Kallupady OHSR retaining wall concrete completed, hand rail and plastering work completed, compound gate work in progress. Kaduvakuzhi retaining wall completed, approach road work completed. Valve chamber 4 Nos completed. PWD NH road cutting permission need to obtain for 0/000- 2/035 Km.Total bill submitted - 38,464,860.00/- ( Road reformation - 22,765,579.00,contractors bill - 35,699,281.00). DBA