rmour layer 1240-m Filter layer -1240m Geo mat - 1240m Gabion - 1240m M40 Pile 470/470- completed,M30 pile 26/26 completed.STP mechanical work ongoing ,Retaining wall- 1240m Retaining wall base 1240m ,Parapet wall-1240,Beam upto 1240m completed Slab rcc-1240m ,Planter box 1240 m chainage completed, Culvert 5nos were completed,Toilet block@ 220 m chainage- completed,600m ch toilet block work completed ,Earthwork excavation upto 1240 m completed, Filling earth work 1240m completed,GSB laying upto 1240m completed ,storm water drain concrete 1240m completed ,Kiosk-completed, Gaseebo work completed; WTP- work completed Pending work :Light pole fittings, sculpture work, KWA connection Financial progress 84% physical 96%