Package: Thalassery Heritage Project - Pazhassi Kovilakam (Mattannur)

11/07/2025 by Abhinandh P T - 9496976373

Ongoing | 21.00% Completed

General Works – Earth filling is 95% complete, and the storytelling wall work is 90% finished. Open Air Theater – column concrete work completed . Pond Renovation – Laterite parapet wall work is in progress. Smithy Mandapam Renovation – Dismantling of MB tiles is finished, and dismantling of the roof truss completed . new truss work completed and MP tile work under progress