Package: Thalassery Heritage Project - Kadirur Surya Narayana Temple

11/07/2025 by Abhinandh P T - 9496976373

Ongoing | 46.00% Completed

Saraswathi Mandapam – 95% complete; polishing and ceiling tile installation pending Toilet Block – 95% complete; ceiling tile installation pending Ootupura – 90% complete; painting and ceiling tile installation pending Pond – Lamp post installation completed; parapet wall construction 30% complete. : paving work - first part of sadarhalli paving started