logo logo-dark

ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)

ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)

Administrative Sanction(Rs)
AS date
No. of Packages
9,750,000
on 30-04-2024
1

ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)

ADDITIONAL WORK AT ECOLODGE CONSTRUCTED AT PEERUMEDU (CONSTRUCTION OF PARKING YARD, COMPOUND FENCING, SERVICE BLOCK, AMBIENT LIGHTING AND MODULAR KITCHEN AT ECOLODGE PEERUMEDU)

Technical Sanction(Rs)
TS date
Project Duration
Contractor
Project Engineer
Project Coordinator
9,750,000
27/09/2022
0 Months
Outlook communications pvt Ltd
-
-
Site Handover Date
Scheduled date of completion
Expected date of completion
Project delay
Date is not specified
Date is not specified
Date is not specified
0 days
Financial Progress
58.81 %
as on
30-04-2024
Total Expenditure(Rs)
4,720,931
Physical Progress
100 %
as on
30-04-2024
Financial Progress Details
2 Bills passed
0 Bills pending
Issues Reported
0 Total issues reported
0 Issues pending
Physical Progress in detail

Component wise progress percentage

Deep Freezer
0.00%
Fencing
100.00%
Diesel Generator
100.00%
Service Block
100.00%
Security Cabin
100.00%
EPABX Installation
100.00%
Electrical Works
100.00%
Refrigerator
0.00%
Microwave Oven
0.00%
Modular Kitchen
100.00%
Steel Almirah
0.00%
Generator Room
100.00%
Civil Work for Lamp Post
0.00%
Last Week Progress
Progress
100.00%

all works completed

Ongoing Work
Progress
%

Planned Vs Achieved