Package: KIIFB Project- Beatification 0f Canals in Alappuzha-Modernizing water Transport in Alappuzha Town Canals and Cleaning of Kappithode Phase II
01/04/2025 by Silppa R - 8606335687
Ongoing | 80.00% Completed
Appendix A: IMPROVEMENT TO SUB CANALS AND BALANCE PROTECTION WORKS TO THE MAIN` CANALS IN ALAPPUZHA TOWN -Side protection works including dismantling, reconstruction in main canals and sub-canals were completed. Appendix B: For Vellappally box culvert-88% of work completed, wing wall construction is under progress. For Arattuvazhi Box culvert - 78% of work completed, top slab concrete is complete, DR & RR work of wing wall is under progress. For Poppy Box culvert - 50% of work completed ,Bottom raft foundation & 2nd lift wall concrete is complete. Appendix C: IMPROVEMENTS OF KAPPITHODE IN AMBALAPUZHA LA CONSTITUENCY AT AMBALAPUZHA SOUTH AND NORTH PANCHAYATH: All work except at hindrance portion completed. Culvert at chainage 4930,6250, 6360, 9660,8580 and 4240 were completed , balance 2 nos to be done only after hindrance cleared. The work on the screen wall has been completed, and drain covering with chequered plate is in progress(77%). .Appendix D: IMPROVEMENTS OF AS CANAL(BALANCE PORTION) AND MADAYANTHODU - At AS canal east side of protection wall at d/s of Kommadi bridge completed. Masonry protection work at LHS (west side), upstream of Pathirapally bridge completed . Pile and slab side protection protection work at road side(East) ,Desilting, Laying coir geo textile and protection work of Madayanthodu are completed. At Arimbu thode side protection work is under progress (53%).At Commercial canal rubble dumping work is completed (100%) and guard stone fixing is under progress (90%).